Northeast Trail – Segment 1 (Piedmont Park)

Piedmont Park (Monroe Drive to Westminster Drive) // Subarea 6

The Northeast Trail – Segment 1 runs 0.9 miles from Monroe Drive to Westminster Drive with a portion through Piedmont Park. This trail closed for construction in August 2023, including the Carriage Trail through Piedmont Park. The BeltLine continues to work alongside Piedmont Park Conservancy, City of Atlanta Parks Department, and Atlanta Department of Transportation on this project. 

Atlanta BeltLine Northeast Trail project map. 04.2023.

Project Status

Construction is underway on this segment that runs alongside Piedmont Park and will be completed in three phases: Phase I from Westminster Drive to Evelyn Street, Phase II from Evelyn Street to Monroe Drive, and Phase III including the 10th Street and Monroe Drive intersection improvements.

  • In Phase I, work is underway to replace an asphalt trail passing through Piedmont Park starting at Westminster Drive NE and running adjacent to Clear Creek. This area is sometimes referred to as the Carriage Trail. This section of trail will have the concrete trail poured to Evelyn Street by early January. Lighting and camera installation will follow along with planting work.
  • Along Phase II, construction crews have completed erosion control measures, tree clearing and stump removal. Storm water work is underway. Grading work is expected to begin in January, along with utility relocation work.
  • Phase III work, which includes pedestrian safety improvements at the intersection of 10th and Monroe Drive, will take place later in the construction schedule and with ample community notice and coordination. Initial planning and logistics are in progress for this phase of work.
  • The BeltLine continues to work alongside Piedmont Park Conservancy, City of Atlanta Parks Department, and Atlanta Department of Transportation on this project. The project is expected to be complete in fall of 2024.

Project Timeline

May 2020 - July 2021
Alternatives analysis and concept validation
July 2021
Locally Preferred Alternative as part of the federally funded, full length of the Northeast Trail design project
July 2021
Execute contract for design phase services
September - October 2021
Gravel installation along unpaved path
August 2023
Groundbreaking and construction start
Fall 2024
Construction expected to be complete